Work History

Kennedy Space Center – Water Damage
February 2012 – Kennedy Space center Life Sciences Lab- Around Noon on February 17, 2012, a six-inch main pipe feeding the fire sprinkler system had cracked in the west stairwell in the three-story, 110,000-square foot facility.  The system, reacting as if a fire required suppression, began pumping water through the pipe at a rate of 1,500 gallons per minute, until it pooled ankle-deep on parts of the second floor and trickled down to the ground floor. The insulated HVAC system was heavily impacted and served as a conduit for the water to run through as well as be trapped in. Mold and other hazards were present and the mitigation/remediation of these was dealt with in coordination with the staff Industrial Hygienists.  In total, approximately 55,000 gallons of water was released into the facility.   75,000 square feet, or 68 percent of the facility, sustained some degree of damage. It was concentrated in office areas on the second floor and mostly spared laboratories and experiments. The project lasted almost two months and resumed normal operations April 16.

 

Industrial Complex – Water Damage
September 2011 Industrial Complex- Wayne, NJ- Warehouse utilized as a distribution center for major retail chains that suffered severe flooding as a result of Hurricane Irene.  The project required water extraction, content manipulation and removal.  Crews working 24 hour shifts resulted in a return to normal business operations in 6 days.  This project was valued at 700k.

 

Government Facility – Water Damage
October 2011 Government Facility- Wilkes-Barre, PA-  450,000sqf facility containing high security inventory damaged by flood waters as a result of Hurricane Irene. This project entailed the removal of approximately 300 tractor trailer loads of inventory requiring destruction under tight security. The facility required extraction and cleaning in order to complete the removal and destruction of the inventory.

 

Schermerhorn Symphony Center – Water Damage
May 2010 – Schermerhorn Symphony Center- We responded to a major flood in Tennessee.  The symphony building had 34 feet of water with in the basement levels leading up to the first floor. This project included pumping water out of flooded areas with constant monitoring of hydrostatic pressure. Climate control of all levels was necessary to protect high end art work, memorabilia, custom furnishings, a 4 million dollar organ along with custom made carpets, wall hangings and fabric. The facility was extremely “High End” and constructed at a cost of 168 million dollars.   We performed controlled demolition, negative air, floor and wall protections, electrical and mechanical evaluations along with constant humidity controls using HOBO detection. This project ran 24 hour shifts consisting of approximately 200 people per shift and required water pump-out, dehumidification, generators, and content pack out.

 

Ocean Downs Casino – Demo/Construction
Ocean Downs Casino –Work performed included: lead and asbestos abatement,  demolition of all non    bearing walls ( steel shell only), installation of new steel to support existing steel, installation of new footers, the addition of the complete second floor for offices and security as well as a third floor viewing area “Judges Bench” for the race calls. The scheduling and coordination of the entire project from start to opening included; electric, mechanical, site work, framing, concrete, glass work, specialty framing, specialty tasks and flooring, This job was quality, time and media sensitive with additional emphasis on professionalism and cleanliness of the project. This job required extended hour shifts during the majority of the project to maintain the projected timeline.
>

 

Marty’s Playland – Fire Damage
April 2008 – Marty’s Playland – Located on the historic boardwalk in Ocean City, Maryland, a fire broke out which affected almost an entire city block consisting of an amusement arcade, restaurant and apartments.  Performing the complete demolition of the restaurant, stabilizing the remaining structure, installing temporary fire walls to separate the “construction zone”, Royal Plus Inc. enabled the arcade to open within a week.  The arcade was dried, cleaned and sanitized with intense building inspections to assure compliance.  The job was time sensitive due to its occurrence “in season” which would bring a detrimental daily loss of income for the business if not open.  Reconstruction began in April 2008 and was totally completed in July.

 

Mercy Medical Center – Water Damage
June 2008- Mercy Medical Center –Royal Plus, Inc. was called to handle a 30,000 sf area affected by flood waters in a hospital.  Upon our arrival, we discovered that the areas damaged were not 30,000 sf but 300,000 sf.  Royal Plus mobilized crews of more than 700 people to handle climate control, demolition, duct cleaning, temp power, temp A/C, air scrubbing, maintain indoor air quality, perform content cleaning & manipulation, ensure equipment protection along with inventory controls. Our specialty team worked with infectious control, engineers and department heads to make sure each area was addressed. We coordinated     demolition with construction to make the transition seamless.  We also built temporary walls in the parking garage then installed temporary   power and climate control to utilize the area as storage for non affected contents.